Meet the Project Team

M50 Concession Ltd has been appointed by the National Roads Authority to carry out the Phase 2 works.  The consortium comprises Spanish firms FCC Construcción S.A., Itinere S.A. and Irish firm PJ Hegarty & Sons.

M50 Concession Ltd’s contract allows them to operate and maintain the M50 motorway from the M1 to the M11 for the next 35 years, and includes 24-hour emergency response and patrols on the motorway together with routine maintenance operations. Meet the rest of the team ...

Phase 2, 2008-2010

The full work zone for Phase 2 is 24km in length and will consist of building a third lane in each direction, upgrading seven junctions and providing a fourth lane between a number of adjacent interchanges.

Some interchanges will become 'FreeFlow' where traffic is not required to stop; some will become 'Partial Free Flow' where traffic will have to stop at traffic signals or yield lines, on one or more approaches.

Northern Section M1–N3

Construction of a third traffic lane in each direction between junction 3 (M1) and junction 6 (N3) plus a fourth auxiliary lane between these interchanges;

Junction 3 (Airport)

Upgrading junction 3 (M1 Interchange above) to a freeflow standard for all M50/M1 traffic movements and building two new bridges and auxiliary lanes to facilitate traffic merging from M1/M50 Interchange and junction 2 (R104 Coolock Lane) north of the Dublin Port Tunnel;

Upgrading junction 4 (Ballymun Interchange), to include a new second lane on all "on" and "off" ramps; providing footpaths and cycle lanes on east and west sides of upgraded junction;

Junction 5 (N2)

Upgrading junction 5 (N2 Interchange above) to a partially freeflow standard including construction of new road bridges, a new footbridge, pedestrian / cycle crossings and cycle paths;

Junction 6 (N3)

Upgrading junction 6 (N3 Interchange above) to a partially freeflow standard and construction of new road bridges, two new footbridges and pedestrian and cycle crossings; replacing the existing roundabout at Auburn Avenue with a new fully signalised junction

24/07/2009 - New content added

Upgrading Junction 7 (N4 Interchange), find below photomontages from the junction overview (further information will be added soon)

Click to see full size image on a new window

24/07/2009 - New content added

Upgrading Junction 9 (N7 Interchange), find below photomontages from the junction overview (further information will be added soon)

Click to see full size image on a new window

Southern Section N81–Sandyford

 

National Roads Authority LogoDepartment of Transport LogoNDP LogoTransport 21Dublin City CouncilSIAC ConstructionFerrovialARUP Logo